More CO2 storage than previously thought for Indiana, Kentucky, Michigan and Ohio

Despite the fact that CCS is extremely expensive, risky, and hard to monitor and is very controversial  --- the studies and push for CCS continues.  It simpley makes no sense to me.....now we find a report  from December 2009 that says we can store about 74% more!  NO THANK YOU!

As a reminder - In Ohio, a large portion of the Mt Simon Sandstone sits below one of the largest fresh water aquifers in the world -  our most precious resource. States are running out of water...

Much of the proposed CO2 to be used for CCS in the midwest comes from ethanol plants.....  in our area we had a great harvest last year with the extra CO2 -  if CCS is so "safe" why are there no plans to  inject it under the cities that produce the bulk of it? 

I do remember reading a study done  in Ohio that said it would not happen in Columbus, Ohio because "it was too urban and densely populated".

The quote below is from the article that is linked below...
The total storage capacity for the region, calculated, using efficiency factors of 0.01 and 0.04, is estimated to be 37.8 and 151.2 billion metric tons of CO2 respectively. This is approximately 74 percent higher than the values of 21.7 and 86.9 billion metric tons of CO2 estimated by the MRCSP for the capacity of the Mount Simon Sandstone in the states of Indiana, Kentucky, Michigan, and Ohio.
 Read the abstract here...

Wednesday, January 27, 2010

Indiana Take Action Today!!! Eminent Domain Bill

http://www.ibj.com/bill-would-give-co2-pipeline-firms-right-to-take-private-land/PARAMS/article/15967
Bill would give CO2 pipeline firms right to take private land
January 25, 2010

A consumer group opposing Senate Bill 115 argues the measure is yet another concession to the developer of a coal-to-methane plant proposed in Rockport, as well as to coal-fired electric utilities that may opt to transport CO2 to underground storage sites.

The measure declares that the transportation of CO2 by pipeline “is declared to be a public use and service, in the public interest, and a benefit to the
welfare of Indiana,” citing its potential to reduce carbon emissions and to promote economic development.

“Granting eminent domain to a private entity is reason enough, we think, to oppose this bill,” said Kerwin Olson, program director for Indianapolis-based Citizens Action Coalition.

The group said the measure is to benefit Indiana Gasification, which in 2006 proposed building a $1.5 billion plant in Spencer County to convert high-sulfur coal to gas. Utilities could use the gas for heating and to generate electricity.

Indiana Gasification, which planned to sell gas to Merrillville-based NIPSCO and Evansville-based Vectren, shelved plans in late-2008 after failing to reach long-term gas supply contracts with utilities, which feared such contracts could impair their long-term credit.

But last March, Gov. Mitch Daniels signed into a law a bill that would allow the Indiana Finance Authority to act as contracting agent between the gasification plant developer and the utilities buying its gas. Daniels has been a supporter of so-called clean-coal technology as an economic development tool and to protect the state’s coal and electric utility industries in the face of punitive carbon-mission regulations contemplated by Congress.

Olson said this marks the fourth year Indiana Gasification has sought various incentives from the state. The principal player in the venture, New York-based Leucadia National Corp., has sought more than $3.6 billion in federal loan guarantees from the Department of Energy for potential gasification plants.

“You’ve got a multi-billion dollar, multi-national corporation that is mandating their agenda through legislation because the business model just doesn’t support it,” Olson said of the proposed plant.

The measure could potentially grant eminent domain powers to numerous firms that plan to ship carbon dioxide trough pipelines.

Duke Energy is studying whether to inject underground the carbon dioxide to be produced at its $2.35 billion Edwardsport electric-generating plant, now under construction. Duke is looking at potential underground storage sites within 50 miles of the plant, but also has looked at piping CO2 to oil wells in southern Illinois as a way to enhance oil extraction.

In addition, Indiana is among Midwest states where Texas-based Denbury Resources is looking to run a 500-mile CO2 pipeline. It could receive carbon from power plants in the state and move it to oil fields in the Gulf of Mexico.

The sponsor of Senate Bill 115, Beverly Gard, R-Greenfield, could not be reached for comment.

Meanwhile, another measure co-sponsored by Gard is drawing fire from CAC. SB 211 would exclude the Indiana Utility Regulatory Commission from ratemaking jurisdiction over private firms that operate carbon-storage facilities or pipelines. Public utilities that hired the private firms could file ask the commission for permission to recover costs from ratepayers.

Moreover, SB 211 declares that carbon dioxide “is not considered a pollutant, a nuisance, a hazardous waste or a deleterious substance.”

CAC argues that the release of CO2 from deep-underground storage sites or from pipelines poses unknown health and environmental risks.

Monday, September 21, 2009

Geological Sequestration Projects Hitting Public Opposition Wall

Last year, Swedish Company Vattenfall announced its plans to go on-line with a major pilot program to test carbon capture and sequestration at a coal-fired power plant. The company recently acknowledged that permitting snags fueled by local opposition render it unable to commence geologic sequestration of captured CO2. Vattenfall intended to begin capturing CO2 at its 30-megawatt Schwarze Pumpe facility, located in Spremberg, Germany, and sequestering it in the nearby Altmark depleted gas field by March or April 2009. Residents of the host-city, however, have expressed concerns about the safety of geological sequestration, preventing the final permitting approval for the site and creating questions about when - or if - the site could be available for any CCS operations.

Vattenfall’s experience at this project is not an isolated incident. Vattenfall reported delays in obtaining approvals for one of its Danish storage projects pointing, in part, to public opposition by local stakeholders. In June, German news sources reported that activists were protesting plans by electric utility RWE to transport captured CO2 by pipeline from a powerplant near Cologne to a sequestration site on Germany’s North Sea Coast. The Wall Street Journal also reported in April that Royal Dutch Shell had run into challenges siting a sequestration facility in Barendrecht, Netherlands, due to grass roots opposition from local residents.

Public opposition is likely to be a critical strategic and legal consideration for US projects. On Friday, August 21, Battelle, the lead partner in a Midwest Regional Carbon Sequestration Partnership project announced that it was abandoning plans to participate in a $92 million public-private demonstration project to site a geological sequestration project in Western Ohio. While the partner cited only “business reasons” for its decision, the reported public opposition to the project could not have helped.

These setbacks illustrate the significant challenges that the siting and permit-approval process can pose, particularly in the face of public opposition, to an otherwise promising project. This will be particularly true during the early stages of a CCS deployment. US policymakers and investors would do well to watch and learn from these early case studies, and to ensure that they devote the legal, political and community relations resources needed to ensure that proposed projects move forward in a realistic and timely fashion.


Link to the above article

http://politicalecology.xyvy.info/?p=1566

Monday, August 10, 2009

German Grassroots Opposition Movement with local political support


To our allies in Germany fighting CO2 sequestration - we are cheering you on!

Click here to be taken to the story

"It was meant to be the world’s first demonstration of a technology that could help save the planet from global warming – a project intended to capture emissions from a coal-fired power station and bury them safely underground.

But the German carbon capture plan has ended with CO2 being pumped directly into the atmosphere, following local opposition at it being stored underground."

Friday, August 7, 2009

Decatur, IL - Large Scale CO2 Sequestration Project


This is a link to a PowerPoint presentation about another Phase III, large-scale CO2 project - shades of what it would look like in Greenville, OH. Click here